Chediston Hall Solar Park (12.3 MW)

Chediston Hall Solar Park is a 12.3 MW solar farm project in East Suffolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 24 May 2013; the record was last updated on 10 May 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12.3 MWsolar farm
operationalstatus in REPD
10 May 2016record last updated
East Suffolkcouncil area

Planning timeline

DateStage
8 October 2012Application submitted
3 January 2013Planning permission granted
4 January 2013Construction started
24 May 2013Operational

Project details

Technology
solar farm
Capacity
12.3 MW
Status (REPD)
operational
Record last updated
10 May 2016
Operator or applicant
Lightsource Renewable Energy
Planning authority
East Suffolk
Planning application reference
DC/12/1119/FUL
Address (REPD)
Land Adjacent To Bonners Farm, Mill Road, Wissett, Suffolk
Council area (by location)
East Suffolk
Time to decision
12 weeks
REPD reference
1717

Who decides

ApplicationsEast SuffolkUK
Decided applications (solar, wind, battery)5510,236
Refused10 (18%)19%
Solar refused3 of 3812%
Onshore wind refused5 of 845%
Battery storage refused2 of 916%
Median time from submission to decision15.0 weeks17.0 weeks
Appeals lodged / allowed0 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Solar Photovoltaic (PV) Farm (Apple Tree)solar farm27approved, not built0.8
Wissett Solar Farm, Wissett Battery Storage (Apple Tree)battery storage10approved, not built0.8
Chediston Hall - 40MW Solar Panelssolar farm40application submitted0.8
Norwich Road Industrial Estatebattery storage50under construction2.4
Hill Farmsolar farm15.9abandoned3.1
Holton Airfieldsolar farm11operational3.7
Upper Holton Wind Farmwind farm11.5operational4.2
Bernard Matthews Wind Farmwind farm11.5application withdrawn4.2
Redisham Hall Farm, School Roadsolar farm42application submitted8.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.3522, 1.4737).