Energy Projects Near You

Clayhill Farm (10 MW solar farm)

Clayhill Farm is a 10 MW solar farm project in Central Bedfordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 24 June 2016; the record was last updated on 7 August 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWsolar farm
operationalstatus in REPD
7 August 2020record last updated
Central Bedfordshirecouncil area

Planning timeline

DateStage
1 September 2014Application submitted
29 January 2015Planning permission granted
24 April 2016Construction started
24 June 2016Operational

Project details

Technology
solar farm
Capacity
10 MW
Status (REPD)
operational
Record last updated
7 August 2020
Operator or applicant
Anesco
Planning authority
Central Bedfordshire
Planning application reference
CB/14/03419/FULL
Site area
36.2 ha
Address (REPD)
North Clayhill Farm, Greenfield Road, Westoning, Bedford, Bedfordshire
Council area (by location)
Central Bedfordshire
Time to decision
21 weeks
REPD reference
2265

Who decides

ApplicationsCentral BedfordshireUK
Decided applications (solar, wind, battery)5910,236
Refused8 (14%)19%
Solar refused4 of 3612%
Onshore wind refused2 of 745%
Battery storage refused2 of 1616%
Median time from submission to decision19.6 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Clayhillbattery storage6operational<0.1
Clayhill Farmbattery storage21operational0.6
Clayhill Farm, Greenfield Roadbattery storage20approved, not built0.9
Greenfield Road, Westoningbattery storage30approved, not built1.0
Greenfield Road - Samphill Solar Farmsolar farm38.4refused2.0
Faldo Farmsolar farm10.8refused3.4
Toddington Services, Hipsey Spinneybattery storage250approved, not built5.0
Hillcrest, Church Roadbattery storage50application withdrawn5.7
Chalgrave Manor, Luton Road Solar Farmsolar farm40approved, not built6.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.9874, -0.4818).