Greenfield Road - Samphill Solar Farm (38.4 MW)

Greenfield Road - Samphill Solar Farm is a 38.4 MW solar farm project in Central Bedfordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 20 February 2026; the record was last updated on 27 April 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

38.4 MWsolar farm
refusedstatus in REPD
27 April 2026record last updated
Central Bedfordshirecouncil area

Planning timeline

DateStage
23 June 2025Application submitted
20 February 2026Refused by the planning authority

Project details

Technology
solar farm
Capacity
38.4 MW
Status (REPD)
refused
Record last updated
27 April 2026
Operator or applicant
Anesco Limited
Planning authority
Central Bedfordshire
Planning application reference
CB/25/02017/FULL
Site area
62.8 ha
Address (REPD)
Samphill Solar Farm, Greenfield Road, Westoning
Council area (by location)
Central Bedfordshire
Time to decision
35 weeks
REPD reference
19175

Earlier applications for this site

ApplicationMWSubmittedOutcome
Greenfield Road - Samphill Solar Farm CB/21/02583/FULL43.54 June 2021withdrawn 30 July 2022

Who decides

ApplicationsCentral BedfordshireUK
Decided applications (solar, wind, battery)5910,236
Refused8 (14%)19%
Solar refused4 of 3612%
Onshore wind refused2 of 745%
Battery storage refused2 of 1616%
Median time from submission to decision19.6 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Clayhillbattery storage6operational2.0
Clayhill Farmsolar farm10operational2.0
Clayhill Farm, Greenfield Roadbattery storage20approved, not built2.1
Clayhill Farmbattery storage21operational2.1
Faldo Farmsolar farm10.8refused2.5
Greenfield Road, Westoningbattery storage30approved, not built2.9
Toddington Services, Hipsey Spinneybattery storage250approved, not built3.6
Hillcrest, Church Roadbattery storage50application withdrawn3.8
Sundon Substationbattery storage49.9operational4.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.9707, -0.4722).