Clyde Wind Farm (350 MW)

Clyde Wind Farm is a 350 MW wind farm project in South Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 October 2012; the record was last updated on 1 June 2018. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

350 MWwind farm
operationalstatus in REPD
1 June 2018record last updated
South Lanarkshirecouncil area

Planning timeline

DateStage
1 October 2004Application submitted
21 July 2008Section 36 consent granted (Scottish Ministers)
1 October 2012Operational

Project details

Technology
wind farm
Capacity
350 MW
Status (REPD)
operational
Record last updated
1 June 2018
Operator or applicant
Scottish and Southern Energy (SSE)/ Greencoat UK Wind
Planning authority
Scottish Government (S36)
Planning application reference
not recorded
Turbines
152
Address (REPD)
Clyde Wind farm, Lowther Hills, between Crawford and Nether Howecleuch, NW of Lockerbie
Council area (by location)
South Lanarkshire
Time to decision
198 weeks
REPD reference
4011

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Whitelaw Brae Wind Farmwind farm57under construction5.3
Tweed Valley, Southern Uplands - Oliver Forest Wind Farmwind farm50.4application submitted5.3
Tweed Valley, Southern Uplands - Oliver Forest Wind Farmbattery storage23application submitted5.3
Earlshaugh Wind Farmwind farm55.2abandoned5.8
Crookedstane Farmwind farm11.4permission expired6.3
Clyde Wind Farm Extension (Clyde 2)wind farm173operational7.0
Elvanfoot, Leadhills Roadbattery storage9.8approved, not built7.5
Elvanfoot, Leadhills Road - Phase 3 - BESSbattery storage25application submitted7.6
Leadhills Road, Elvanfoot Phase 2battery storage49.9application submitted7.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.4416, -3.5427).