Crookedstane Farm (11.4 MW wind farm)

Crookedstane Farm is an 11.4 MW wind farm project in South Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 19 January 2019; the record was last updated on 16 December 2019.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11.4 MWwind farm
permission expiredstatus in REPD
16 December 2019record last updated
South Lanarkshirecouncil area

Planning timeline

DateStage
13 June 2013Application submitted
19 January 2016Planning permission granted
19 January 2019Permission expired

Project details

Technology
wind farm
Capacity
11.4 MW
Status (REPD)
permission expired
Record last updated
16 December 2019
Operator or applicant
BayWa r.e. (formerly Forsa)
Planning authority
South Lanarkshire
Planning application reference
CL/13/0206
Turbines
4
Turbine height
127 m
Address (REPD)
Land at Crookedstane Farm Elvanfoot
Council area (by location)
South Lanarkshire
Time to decision
136 weeks
REPD reference
4355

Who decides

ApplicationsSouth LanarkshireUK
Decided applications (solar, wind, battery)8910,236
Refused30 (34%)19%
Solar refused2 of 2012%
Onshore wind refused21 of 5645%
Battery storage refused7 of 1316%
Median time from submission to decision47.4 weeks17.0 weeks
Appeals lodged / allowed6 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Elvanfoot, Leadhills Roadbattery storage9.8approved, not built2.7
Elvanfoot, Leadhills Road - Phase 3 - BESSbattery storage25application submitted2.8
Leadhills Road, Elvanfoot Phase 2battery storage49.9application submitted2.9
Lion Hill Wind Farm (Crookedstane Farm 2)wind farm11.4permission expired5.0
Harryburn Wind Farmwind farm67refused on appeal6.3
Clyde Wind Farmwind farm350operational6.3
Wind farm at Rivox Wind Farm Lowther Hills West Of Moffatwind farm208application submitted8.8
Watchman Energy Parkbattery storage50application submitted9.8
Watchman Energy Parkwind farm91application submitted9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.4195, -3.635).