Energy Projects Near You

Colton Mill Farm & Cawarden Springs Farm (49.9 MW solar farm)

Colton Mill Farm & Cawarden Springs Farm is a 49.9 MW solar farm project in Lichfield, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 1 November 2021, not yet built; the record was last updated on 7 December 2021. REPD records the planning permission as expiring on 1 November 2024, but the project holds a Contracts for Difference award (AR4), so construction may have started. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtmay be out of datestatus in REPD
7 December 2021record last updated
Lichfieldcouncil area

REPD records the planning permission as expiring on 1 November 2024, but the project holds a Contracts for Difference award (AR4), so construction may have started.

Planning timeline

DateStage
21 January 2021Application submitted
1 November 2021Planning permission granted
1 November 2024Permission expired

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
7 December 2021
Operator or applicant
Spring Dev 07 Limited
Planning authority
Lichfield
Planning application reference
21/00359/FULM
Site area
62.8 ha
Address (REPD)
Land At Colton Mill Farm And Cawarden Springs Farm Blithbury Road Colton Rugeley Staffordshire
Council area (by location)
Lichfield
Time to decision
41 weeks
Contracts for Difference
AR4
Name in REPD
Colton Mill Farm & Cawarden Springs Farm - Solar Panels
REPD reference
8813

Who decides

ApplicationsLichfieldUK
Decided applications (solar, wind, battery)1310,236
Refused2 (15%)19%
Solar refused0 of 1012%
Onshore wind refused1 of 145%
Battery storage refused1 of 216%
Median time from submission to decision24.7 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Armitage Road, Armitagebattery storage200refused1.0
Former Rugeley Power Stationbattery storage49.9abandoned1.1
Black Flatts Solar Farmsolar farm49.9approved, not built1.2
Hawkesyard Estate, Rugeley Roadbattery storage100application submitted2.0
Moreton Brook Farm, Lea Lane Solar Farmsolar farm49.9approved, not built7.4
Bleak Housewind farm6.5application withdrawn8.2
Lower Farm, Drointon Lane Solar farm & Battery Energy Storagesolar farm49.9approved, not built9.4
Bagot's Parkwind farm18.4refused9.5
Yew Tree Farm, Drointon Lanesolar farm49application submitted9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.7622, -1.908).