Craiginmoddie Wind Farm (92.4 MW)

Craiginmoddie Wind Farm is a 92.4 MW wind farm project in South Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 5 November 2025, not yet built; the record was last updated on 6 January 2026. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

92.4 MWwind farm
approved, not builtstatus in REPD
6 January 2026record last updated
South Ayrshirecouncil area

Planning timeline

DateStage
21 January 2021Application submitted
5 November 2025Section 36 consent granted (Scottish Ministers)
5 November 2028Permission due to expire (unless work starts)

Project details

Technology
wind farm
Capacity
92.4 MW
Status (REPD)
approved, not built
Record last updated
6 January 2026
Operator or applicant
Energiekontor (UK) Limited
Planning authority
Scottish Government (S36)
Planning application reference
ECU00002196
Turbines
14
Turbine height
200 m
Address (REPD)
Craiginmoddie U27 From B741 Junction At Cloyntie To U66 Junction At South Balloch Maybole South Ayrshire
Council area (by location)
South Ayrshire
Time to decision
250 weeks
REPD reference
7877

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Knoweside Hillwind farm19.5application withdrawn4.8
Nethermainssolar farm5abandoned5.6
Kirk Hill Wind Farmwind farm18.8operational6.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.3545, -4.6811).