Energy Projects Near You

Kirk Hill Wind Farm (18.8 MW)

Kirk Hill Wind Farm is an 18.8 MW wind farm project in South Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 May 2024; the record was last updated on 28 May 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18.8 MWwind farm
operationalstatus in REPD
28 May 2024record last updated
South Ayrshirecouncil area

Planning timeline

DateStage
29 January 2015Application submitted
2 March 2016Refused by the planning authority
31 May 2016Appeal lodged
16 February 2017Planning permission granted
16 February 2017Appeal allowed
1 September 2022Construction started
1 May 2024Operational

Project details

Technology
wind farm
Capacity
18.8 MW
Status (REPD)
operational
Record last updated
28 May 2024
Operator or applicant
Corolis Energy/ ESB / Ripple Energy
Planning authority
South Ayrshire
Planning application reference
14/01646/APPM
Appeal reference
PPA-370-2052
Turbines
8
Turbine height
110 m
Address (REPD)
Wallacetown-North West To, Hallowshean Cottage, Maybole, Strathclyde
Council area (by location)
South Ayrshire
Time to decision
107 weeks
Contracts for Difference
AR6
REPD reference
4988

Who decides

ApplicationsSouth AyrshireUK
Decided applications (solar, wind, battery)2010,236
Refused12 (60%)19%
Solar refused0 of 612%
Onshore wind refused12 of 1345%
Battery storage refused0 of 116%
Median time from submission to decision41.7 weeks17.0 weeks
Appeals lodged / allowed5 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Nethermainssolar farm5abandoned5.4
Hadyard Hillwind farm120operational5.5
Hadyard Hill extensionwind farm88application withdrawn5.8
Craiginmoddie Wind Farmwind farm92.4approved, not built6.5
Tralorg Wind Farmwind farm20operational7.6
Knoweside Hillwind farm19.5application withdrawn8.6
Assel Valley Wind Farmwind farm25operational9.2
Knockskae Wind Farmwind farm25.3refused10.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.3064, -4.7399).