Tralorg Wind Farm (20 MW)

Tralorg Wind Farm is a 20 MW wind farm project in South Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 June 2020; the record was last updated on 14 September 2021.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWwind farm
operationalstatus in REPD
14 September 2021record last updated
South Ayrshirecouncil area

Planning timeline

DateStage
10 February 2011Application submitted
22 March 2013Refused by the planning authority
21 February 2014Planning permission granted
21 February 2014Appeal allowed
14 February 2017Construction started
1 June 2020Operational

Project details

Technology
wind farm
Capacity
20 MW
Status (REPD)
operational
Record last updated
14 September 2021
Operator or applicant
RPMI Railpen (formerly BayWa)
Planning authority
South Ayrshire
Planning application reference
11/01569/APPM
Appeal reference
13/00014/REFUSA
Turbines
8
Address (REPD)
2km to the east of Girvan
Council area (by location)
South Ayrshire
Time to decision
158 weeks
Contracts for Difference
AR1
REPD reference
4073

Who decides

ApplicationsSouth AyrshireUK
Decided applications (solar, wind, battery)2010,236
Refused12 (60%)19%
Solar refused0 of 612%
Onshore wind refused12 of 1345%
Battery storage refused0 of 116%
Median time from submission to decision41.7 weeks17.0 weeks
Appeals lodged / allowed5 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Assel Valley Wind Farmwind farm25operational3.1
Kilgalliochbattery storage100approved, not built3.5
Hadyard Hillwind farm120operational4.8
Hadyard Hill extensionwind farm88application withdrawn5.3
Knockodhar Wind Farmwind farm100application submitted7.4
Kirk Hill Wind Farmwind farm18.8operational7.6
Millenderdale Wind Farmwind farm15refused on appeal9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.2498, -4.8062).