Energy Projects Near You

Solar, wind and battery projects near Girvan (KA26)

13 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of KA26 (South Ayrshire): 3 are waiting for a planning decision, 2 approved but not yet running, 4 operational. The largest live scheme is Kilgallioch (100 MW battery storage, approved on 16 July 2024, not yet built), 2.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

13projects within 10 km
3awaiting a decision
2approved, not running
4operational

Projects within 10 km of KA26

Projects of 1 MW and more (12)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Kilgalliochbattery storagebattery storage100approved, not builtupdated Aug 2025Jan 2021granted Jul 2024Aug 2025South Ayrshire2.4
Assel Valley Wind Farmwind farmwind farm25operationalupdated Apr 2017Jun 2011granted Sep 2013Apr 2017South Ayrshire3.8
Tralorg Wind Farmwind farmwind farm20operationalupdated Sep 2021Feb 2011granted Feb 2014Sep 2021South Ayrshire4.1
Ladywell Avenuewind turbinewind turbine1application submitted may be out of dateupdated Jan 2024Dec 2023—Jan 2024South Ayrshire5.1
Millenderdale Wind Farmwind farmwind farm15refused on appealupdated Jun 2020Jun 2014refused Mar 2019Jun 2020South Ayrshire5.2
Dalquhandy Windfarmwind farmwind farm42operationalupdated Jan 2026Feb 2012granted Jan 2015Jan 2026South Ayrshire6.2
Breaker Hillwind farmwind farm7.2refused on appealupdated Mar 2015Nov 2013refused Jun 2014Mar 2015South Ayrshire6.5
Straid Farm Wind Parkwind farmwind farm36.8refused on appealupdated Feb 2016Aug 2011refused May 2015Feb 2016South Ayrshire7.5
Knockodhar Wind Farmwind farmwind farm100application submitted may be out of dateupdated Jul 2023May 2023—Jul 2023South Ayrshire7.9
Knockodhar Wind Farmbattery storagebattery storage20application submitted may be out of dateupdated Jul 2023May 2023—Jul 2023South Ayrshire7.9
Hadyard Hillwind farmwind farm120operationalupdated May 2009May 2003granted Dec 2003May 2009South Ayrshire8.0
Hadyard Hill extensionwind farmwind farm88application withdrawnupdated Nov 2017Apr 2015—Nov 2017South Ayrshire8.3
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Ladywell Avenuerooftop solarrooftop solar0.2approved, not built may be out of dateupdated Feb 2023Dec 2022granted Feb 2023Feb 2023South Ayrshire5.1

Distance from the average position of the KA26 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Rooftop solar101000.2
Wind farm91043100
Wind turbine110001
Battery storage21100120

MW in pipeline: pending, approved and under-construction capacity.

How South Ayrshire decides solar, wind and battery applications

ApplicationsSouth AyrshireUK
Decided applications (solar, wind, battery)2010,236
Refused12 (60%)19%
Solar refused0 of 612%
Onshore wind refused12 of 1345%
Battery storage refused0 of 116%
Median time from submission to decision41.7 weeks17.0 weeks
Appeals lodged / allowed5 / 3—

All projects in South Ayrshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near KA26, 4 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.