Breaker Hill (7.2 MW wind farm)

Breaker Hill is a 7.2 MW wind farm project in South Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 2 February 2015; the record was last updated on 12 March 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7.2 MWwind farm
refused on appealstatus in REPD
12 March 2015record last updated
South Ayrshirecouncil area

Planning timeline

DateStage
28 November 2013Application submitted
19 June 2014Refused by the planning authority
18 September 2014Appeal lodged
2 February 2015Appeal refused

Project details

Technology
wind farm
Capacity
7.2 MW
Status (REPD)
refused on appeal
Record last updated
12 March 2015
Operator or applicant
Wind Prospect Developments
Planning authority
South Ayrshire
Planning application reference
13/01310/APP
Appeal reference
PPA-370-2043
Turbines
9
Address (REPD)
The site is located 8km South of Girvan between Pinwherry and Colmonell
Council area (by location)
South Ayrshire
Time to decision
29 weeks
REPD reference
4102

Earlier applications for this site

ApplicationMWSubmittedOutcome
Breaker Hill 09/00979/APP19.54 September 2009refused 15 March 2012

Who decides

ApplicationsSouth AyrshireUK
Decided applications (solar, wind, battery)2010,236
Refused12 (60%)19%
Solar refused0 of 612%
Onshore wind refused12 of 1345%
Battery storage refused0 of 116%
Median time from submission to decision41.7 weeks17.0 weeks
Appeals lodged / allowed5 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Millenderdale Wind Farmwind farm15refused on appeal1.7
Dalquhandy Windfarmwind farm42operational3.5
Straid Farm Wind Parkwind farm36.8refused on appeal4.0
Kilgalliochbattery storage100approved, not built8.3
Mark Hillwind farm56operational8.4
Assel Valley Wind Farmwind farm25operational9.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.1607, -4.8663).