Energy Projects Near You

Kilgallioch (100 MW battery storage)

Kilgallioch is a 100 MW battery storage project in South Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 16 July 2024, not yet built; the record was last updated on 26 August 2025. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

100 MWbattery storage
approved, not builtstatus in REPD
26 August 2025record last updated
South Ayrshirecouncil area

Planning timeline

DateStage
13 January 2021Application submitted
16 July 2024Section 36 consent granted (Scottish Ministers)
16 July 2027Permission due to expire (unless work starts)

Project details

Technology
battery storage (co-located with re)
Capacity
100 MW
Status (REPD)
approved, not built
Record last updated
26 August 2025
Operator or applicant
Scottish Power Renewables
Planning authority
Scottish Government (S36)
Planning application reference
ECU00002197
Address (REPD)
Wind Farm, Kilgallioch C72 From Gowlands Terrace, Barrhill To Council Boundary S/O Chirmorrie South From Barrhill, Barrhill, Girvan
Council area (by location)
South Ayrshire
Time to decision
183 weeks
Name in REPD
Kilgallioch - Battery energy storage
REPD reference
9007

Recorded together with Kilgallioch wind farm (239 MW wind farm, operational).

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Tralorg Wind Farmwind farm20operational3.5
Assel Valley Wind Farmwind farm25operational5.0
Millenderdale Wind Farmwind farm15refused on appeal6.7
Dalquhandy Windfarmwind farm42operational6.9
Straid Farm Wind Parkwind farm36.8refused on appeal8.1
Hadyard Hillwind farm120operational8.2
Breaker Hillwind farm7.2refused on appeal8.3
Hadyard Hill extensionwind farm88application withdrawn8.7
Knockodhar Wind Farmwind farm100application submitted9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.2349, -4.8556).