Energy Projects Near You

Kilgallioch wind farm (239 MW)

Kilgallioch wind farm is a 239 MW wind farm project in Dumfries and Galloway, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 December 2017; the record was last updated on 22 February 2018. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

239 MWwind farm
operationalstatus in REPD
22 February 2018record last updated
Dumfries and Gallowaycouncil area

Planning timeline

DateStage
5 March 2010Application submitted
21 February 2013Section 36 consent granted (Scottish Ministers)
28 July 2015Construction started
15 December 2017Operational

Project details

Technology
wind farm
Capacity
239 MW
Status (REPD)
operational
Record last updated
22 February 2018
Operator or applicant
Scottish Power Renewables
Planning authority
Scottish Government (S36)
Planning application reference
not recorded
Turbines
96
Address (REPD)
(Arecloch Phase 2) land five kilometres to the south of Barrhill, five kilometres to the northeast of New Luce and 11km to the northwest of Kirkcowan
Council area (by location)
Dumfries and Galloway
Time to decision
155 weeks
REPD reference
4386

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Artfield Fellwind farm19.5operational2.6
Glenchamber Wind Farmwind farm27.5operational4.1
Kilgallioch Windfarm (Extension Solar)solar farm20abandoned4.2
Kilgallioch Windfarm (Extension)wind farm50.4under construction4.2
Gass Wind Farmwind farm20.7permission expired5.4
Stranoch 2wind farm84approved, not built5.5
Garvilland Farmwind farm18approved, not built7.7
Wind Turbines at High Mark Wind Farm 5km Ne/O Cairnryanwind farm50.4application submitted8.5
Wind Turbines at High Mark Wind Farm 5km Ne/O Cairnryanbattery storage15application submitted8.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.9885, -4.8017).