Energy Projects Near You

Wind Turbines at High Mark Wind Farm 5km Ne/O Cairnryan (15 MW)

Wind Turbines at High Mark Wind Farm 5km Ne/O Cairnryan is a 15 MW battery storage project in Dumfries and Galloway, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 15 May 2026, no decision recorded; the record was last updated on 22 June 2026. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15 MWbattery storage
application submittedstatus in REPD
22 June 2026record last updated
Dumfries and Gallowaycouncil area

Planning timeline

DateStage
15 May 2026Application submitted

Project details

Technology
battery storage (stand-alone storage)
Capacity
15 MW
Status (REPD)
application submitted
Record last updated
22 June 2026
Operator or applicant
Wind Estate (UK) Ltd
Planning authority
Scottish Government (S36)
Planning application reference
ECU00005159
Address (REPD)
High Mark Wind Farm 5km Ne/O Cairnryan, 7.5km Se/O New Luce, Newton Stewart
Council area (by location)
Dumfries and Galloway
Name in REPD
High Mark Wind Farm - Wind Turbines
REPD reference
16807

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Wind Turbines at High Mark Wind Farm 5km Ne/O Cairnryanwind farm50.4application submitted<0.1
Stranoch 2wind farm84approved, not built3.1
Glen Appwind farm22operational3.6
Mid Moile Wind Farmwind farm99.4approved, not built6.2
Kilgallioch wind farmwind farm239operational8.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.997, -4.934).