Glen App (22 MW wind farm)

Glen App is a 22 MW wind farm project in Dumfries and Galloway, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 January 2017; the record was last updated on 19 July 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

22 MWwind farm
operationalstatus in REPD
19 July 2017record last updated
Dumfries and Gallowaycouncil area

Planning timeline

DateStage
2 October 2012Application submitted
4 June 2015Planning permission granted
13 October 2016Construction started
15 January 2017Operational

Project details

Technology
wind farm
Capacity
22 MW
Status (REPD)
operational
Record last updated
19 July 2017
Operator or applicant
Scottish Power Renewables
Planning authority
Dumfries and Galloway
Planning application reference
12/01156/APPM
Turbines
11
Address (REPD)
NE/o Cairnryan, Stranraer, Dumfries and Galloway
Council area (by location)
Dumfries and Galloway
Time to decision
139 weeks
REPD reference
4593

Who decides

ApplicationsDumfries and GallowayUK
Decided applications (solar, wind, battery)10610,236
Refused40 (38%)19%
Solar refused1 of 1812%
Onshore wind refused33 of 7245%
Battery storage refused6 of 1616%
Median time from submission to decision60.9 weeks17.0 weeks
Appeals lodged / allowed19 / 17—

Other large projects within 10 km

ProjectTypeMWStatuskm
Mid Moile Wind Farmwind farm99.4approved, not built3.0
Wind Turbines at High Mark Wind Farm 5km Ne/O Cairnryanbattery storage15application submitted3.6
Wind Turbines at High Mark Wind Farm 5km Ne/O Cairnryanwind farm50.4application submitted3.6
Stranoch 2wind farm84approved, not built6.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.0007, -4.9897).