Glenchamber Wind Farm (27.5 MW)

Glenchamber Wind Farm is a 27.5 MW wind farm project in Dumfries and Galloway, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 June 2016; the record was last updated on 4 April 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

27.5 MWwind farm
operationalstatus in REPD
4 April 2017record last updated
Dumfries and Gallowaycouncil area

Planning timeline

DateStage
28 October 2010Application submitted
30 September 2011Refused by the planning authority
31 July 2012Planning permission granted
31 July 2012Appeal allowed
6 February 2015Construction started
1 June 2016Operational

Project details

Technology
wind farm
Capacity
27.5 MW
Status (REPD)
operational
Record last updated
4 April 2017
Operator or applicant
Renewable Energy Systems (RES)
Planning authority
Dumfries and Galloway
Planning application reference
10/P/1/0494
Turbines
11
Address (REPD)
between New Luce, Kirkcowan and Glenluce
Council area (by location)
Dumfries and Galloway
Time to decision
92 weeks
REPD reference
4638

Who decides

ApplicationsDumfries and GallowayUK
Decided applications (solar, wind, battery)10610,236
Refused40 (38%)19%
Solar refused1 of 1812%
Onshore wind refused33 of 7245%
Battery storage refused6 of 1616%
Median time from submission to decision60.9 weeks17.0 weeks
Appeals lodged / allowed19 / 17—

Other large projects within 10 km

ProjectTypeMWStatuskm
Gass Wind Farmwind farm20.7permission expired1.5
Artfield Fellwind farm19.5operational1.5
Kilgallioch Windfarm (Extension Solar)solar farm20abandoned3.5
Kilgallioch Windfarm (Extension)wind farm50.4under construction3.5
Kilgallioch wind farmwind farm239operational4.1
Garvilland Farmwind farm18approved, not built5.4
Shennanton Wind Farmwind farm30refused on appeal9.0
Stranoch 2wind farm84approved, not built9.3
BARLOCKHART MOOR - extensionwind farm8.2permission expired9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.9634, -4.7543).