Garvilland Farm (18 MW wind farm)

Garvilland Farm is an 18 MW wind farm project in Dumfries and Galloway, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 27 January 2026, not yet built; the record was last updated on 12 May 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18 MWwind farm
approved, not builtstatus in REPD
12 May 2026record last updated
Dumfries and Gallowaycouncil area

Planning timeline

DateStage
12 April 2021Application submitted
27 January 2026Planning permission granted
27 January 2029Permission due to expire (unless work starts)

Project details

Technology
wind farm
Capacity
18 MW
Status (REPD)
approved, not built
Record last updated
12 May 2026
Operator or applicant
Green Cat Renewables Limited
Planning authority
Dumfries and Galloway
Planning application reference
21/0595/FUL
Turbines
5
Turbine height
150 m
Address (REPD)
Garvilland Farm, Glenluce, Newton Stewart, Dumfries and Galloway
Council area (by location)
Dumfries and Galloway
Time to decision
250 weeks
REPD reference
6751

Who decides

ApplicationsDumfries and GallowayUK
Decided applications (solar, wind, battery)10610,236
Refused40 (38%)19%
Solar refused1 of 1812%
Onshore wind refused33 of 7245%
Battery storage refused6 of 1616%
Median time from submission to decision60.9 weeks17.0 weeks
Appeals lodged / allowed19 / 17—

Other large projects within 10 km

ProjectTypeMWStatuskm
Barlockhart Moor Wind Turbineswind farm8.4approved, not built4.8
BARLOCKHART MOOR - extensionwind farm8.2permission expired5.0
Glenchamber Wind Farmwind farm27.5operational5.4
Artfield Fellwind farm19.5operational5.7
Gass Wind Farmwind farm20.7permission expired6.0
Barlockhart Moorwind farm8.1operational6.0
Kilgallioch wind farmwind farm239operational7.7
Carscreugh Renewable Energy Parkwind farm15.3operational7.8
Annabaglish Wind Farmwind farm35refused on appeal8.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.9195, -4.7896).