Annabaglish Wind Farm (35 MW)

Annabaglish Wind Farm is a 35 MW wind farm project in Dumfries and Galloway, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 26 February 2018; the record was last updated on 28 February 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

35 MWwind farm
refused on appealstatus in REPD
28 February 2018record last updated
Dumfries and Gallowaycouncil area

Planning timeline

DateStage
31 October 2013Application submitted
12 July 2017Refused by the planning authority
11 October 2017Appeal lodged
26 February 2018Appeal refused

Project details

Technology
wind farm
Capacity
35 MW
Status (REPD)
refused on appeal
Record last updated
28 February 2018
Operator or applicant
Renewable Energy Systems (RES)
Planning authority
Dumfries and Galloway
Planning application reference
13/P/1/0351
Appeal reference
PPA-170-2127
Turbines
14
Address (REPD)
ANNABAGLISH, NEAR GLENLUCE
Council area (by location)
Dumfries and Galloway
Time to decision
193 weeks
REPD reference
4486

Who decides

ApplicationsDumfries and GallowayUK
Decided applications (solar, wind, battery)10610,236
Refused40 (38%)19%
Solar refused1 of 1812%
Onshore wind refused33 of 7245%
Battery storage refused6 of 1616%
Median time from submission to decision60.9 weeks17.0 weeks
Appeals lodged / allowed19 / 17—

Other large projects within 10 km

ProjectTypeMWStatuskm
Carscreugh Renewable Energy Parkwind farm15.3operational4.5
BARLOCKHART MOOR - extensionwind farm8.2permission expired5.8
Barlockhart Moor Wind Turbineswind farm8.4approved, not built7.3
Barlockhart Moorwind farm8.1operational7.5
Shennanton Wind Farmwind farm30refused on appeal8.1
Garvilland Farmwind farm18approved, not built8.1
Shennanton Wind Farmwind farm30application submitted8.4
Gass Wind Farmwind farm20.7permission expired9.0
Airies Farmwind farm35operational9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.887, -4.6761).