Annabaglish Wind Farm (35 MW)
Annabaglish Wind Farm is a 35 MW wind farm project in Dumfries and Galloway, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 26 February 2018; the record was last updated on 28 February 2018.
35 MWwind farm
refused on appealstatus in REPD
28 February 2018record last updated
Dumfries and Gallowaycouncil area
Planning timeline
| Date | Stage |
|---|---|
| 31 October 2013 | Application submitted |
| 12 July 2017 | Refused by the planning authority |
| 11 October 2017 | Appeal lodged |
| 26 February 2018 | Appeal refused |
Project details
- Technology
- wind farm
- Capacity
- 35 MW
- Status (REPD)
- refused on appeal
- Record last updated
- 28 February 2018
- Operator or applicant
- Renewable Energy Systems (RES)
- Planning authority
- Dumfries and Galloway
- Planning application reference
- 13/P/1/0351
- Appeal reference
- PPA-170-2127
- Turbines
- 14
- Address (REPD)
- ANNABAGLISH, NEAR GLENLUCE
- Council area (by location)
- Dumfries and Galloway
- Time to decision
- 193 weeks
- REPD reference
- 4486
Who decides
| Applications | Dumfries and Galloway | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 106 | 10,236 |
| Refused | 40 (38%) | 19% |
| Solar refused | 1 of 18 | 12% |
| Onshore wind refused | 33 of 72 | 45% |
| Battery storage refused | 6 of 16 | 16% |
| Median time from submission to decision | 60.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 19 / 17 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Carscreugh Renewable Energy Park | wind farm | 15.3 | operational | 4.5 |
| BARLOCKHART MOOR - extension | wind farm | 8.2 | permission expired | 5.8 |
| Barlockhart Moor Wind Turbines | wind farm | 8.4 | approved, not built | 7.3 |
| Barlockhart Moor | wind farm | 8.1 | operational | 7.5 |
| Shennanton Wind Farm | wind farm | 30 | refused on appeal | 8.1 |
| Garvilland Farm | wind farm | 18 | approved, not built | 8.1 |
| Shennanton Wind Farm | wind farm | 30 | application submitted | 8.4 |
| Gass Wind Farm | wind farm | 20.7 | permission expired | 9.0 |
| Airies Farm | wind farm | 35 | operational | 9.5 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.887, -4.6761).