BARLOCKHART MOOR - extension (8.2 MW wind farm)

BARLOCKHART MOOR - extension is an 8.2 MW wind farm project in Dumfries and Galloway, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 21 May 2021; the record was last updated on 11 March 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8.2 MWwind farm
permission expiredstatus in REPD
11 March 2020record last updated
Dumfries and Gallowaycouncil area

Planning timeline

DateStage
25 March 2013Application submitted
15 September 2015Planning permission granted
21 May 2021Permission expired

Project details

Technology
wind farm
Capacity
8.2 MW
Status (REPD)
permission expired
Record last updated
11 March 2020
Operator or applicant
West Coast Energy
Planning authority
Dumfries and Galloway
Planning application reference
13/P/1/0136
Turbines
4
Address (REPD)
BARLOCKHART MOOR, GLENLUCE
Council area (by location)
Dumfries and Galloway
Time to decision
129 weeks
REPD reference
4491

Who decides

ApplicationsDumfries and GallowayUK
Decided applications (solar, wind, battery)10610,236
Refused40 (38%)19%
Solar refused1 of 1812%
Onshore wind refused33 of 7245%
Battery storage refused6 of 1616%
Median time from submission to decision60.9 weeks17.0 weeks
Appeals lodged / allowed19 / 17—

Other large projects within 10 km

ProjectTypeMWStatuskm
Barlockhart Moor Wind Turbineswind farm8.4approved, not built1.6
Barlockhart Moorwind farm8.1operational1.9
Carscreugh Renewable Energy Parkwind farm15.3operational3.1
Garvilland Farmwind farm18approved, not built5.0
Annabaglish Wind Farmwind farm35refused on appeal5.8
Glenchamber Wind Farmwind farm27.5operational9.6
Gass Wind Farmwind farm20.7permission expired9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.8772, -4.7651).