Mark Hill (56 MW wind farm)

Mark Hill is a 56 MW wind farm project in South Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 June 2011; the record was last updated on 16 August 2011. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

56 MWwind farm
operationalstatus in REPD
16 August 2011record last updated
South Ayrshirecouncil area

Planning timeline

DateStage
19 August 2005Application submitted
1 June 2008Section 36 consent granted (Scottish Ministers)
1 October 2009Construction started
1 June 2011Operational

Project details

Technology
wind farm
Capacity
56 MW
Status (REPD)
operational
Record last updated
16 August 2011
Operator or applicant
Force 9 Energy
Planning authority
Scottish Government (S36)
Planning application reference
not recorded
Turbines
24
Address (REPD)
Mark's Hill, Barrhill
Council area (by location)
South Ayrshire
Time to decision
145 weeks
REPD reference
3260

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Altercannoch Wind Farmwind farm27.7refused on appeal5.0
Chirmorie Wind Farmwind farm80approved, not built5.7
Clauchrie Windfarm Batterybattery storage25refused5.9
Clauchrie Windfarmwind farm100refused5.9
Corwar Wind Farmwind farm16.4refused on appeal6.1
Arecleoch Wind Farm (extension)wind farm72.8under construction7.4
Arecleoch Windfarmwind farm120operational7.4
Arecleoch Wind Farm (extension)battery storage20under construction7.4
Breaker Hillwind farm7.2refused on appeal8.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.1284, -4.7463).