Energy Projects Near You

Clauchrie Windfarm Battery (25 MW)

Clauchrie Windfarm Battery is a 25 MW battery storage project in South Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 31 August 2023; the record was last updated on 23 September 2020. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

25 MWbattery storage
refusedstatus in REPD
23 September 2020record last updated
South Ayrshirecouncil area

Planning timeline

DateStage
18 December 2019Application submitted
31 August 2023Refused by the planning authority

Project details

Technology
battery storage (co-located with re)
Capacity
25 MW
Status (REPD)
refused
Record last updated
23 September 2020
Operator or applicant
Scottish Power Renewables
Planning authority
Scottish Government (S36)
Planning application reference
ECU00002001
Address (REPD)
Clauchrie Windfarm, 6KM North-East Of, Barhill, Newton Stewart, Dumfries and Galloway
Council area (by location)
South Ayrshire
Time to decision
193 weeks
REPD reference
7804

Recorded together with Clauchrie Windfarm (100 MW wind farm, refused).

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Knockodhar Wind Farmwind farm100application submitted5.7
Mark Hillwind farm56operational5.9
Corwar Wind Farmwind farm16.4refused on appeal8.4
Balunton Wind Farmwind farm27application withdrawn9.5
Assel Valley Wind Farmwind farm25operational9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.1634, -4.6772).