Arecleoch Windfarm (120 MW)

Arecleoch Windfarm is a 120 MW wind farm project in South Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 14 June 2011; the record was last updated on 25 October 2011. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

120 MWwind farm
operationalstatus in REPD
25 October 2011record last updated
South Ayrshirecouncil area

Planning timeline

DateStage
3 April 2006Application submitted
1 June 2008Section 36 consent granted (Scottish Ministers)
1 September 2009Construction started
14 June 2011Operational

Project details

Technology
wind farm
Capacity
120 MW
Status (REPD)
operational
Record last updated
25 October 2011
Operator or applicant
Scottish Power Renewables
Planning authority
Scottish Government (S36)
Planning application reference
not recorded
Turbines
60
Address (REPD)
Arecleoch and Kilgallioch Forest near Barrhill
Council area (by location)
South Ayrshire
Time to decision
113 weeks
REPD reference
3258

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Arecleoch Wind Farm (extension)wind farm72.8under construction<0.1
Arecleoch Wind Farm (extension)battery storage20under construction<0.1
Chirmorie Wind Farmwind farm80approved, not built1.7
Altercannoch Wind Farmwind farm27.7refused on appeal3.3
Mark Hillwind farm56operational7.4
Corwar Wind Farmwind farm16.4refused on appeal7.7
Kilgallioch wind farmwind farm239operational8.9
Kilgallioch Windfarm (Extension)wind farm50.4under construction9.2
Kilgallioch Windfarm (Extension Solar)solar farm20abandoned9.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.0688, -4.7971).