Altercannoch Wind Farm (27.7 MW)

Altercannoch Wind Farm is a 27.7 MW wind farm project in South Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 1 March 2019; the record was last updated on 26 March 2019.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

27.7 MWwind farm
refused on appealstatus in REPD
26 March 2019record last updated
South Ayrshirecouncil area

Planning timeline

DateStage
22 December 2015Application submitted
16 November 2017Refused by the planning authority
15 February 2018Appeal lodged
1 March 2019Appeal refused

Project details

Technology
wind farm
Capacity
27.7 MW
Status (REPD)
refused on appeal
Record last updated
26 March 2019
Operator or applicant
Brookfield Renewable UK
Planning authority
South Ayrshire
Planning application reference
not recorded
Appeal reference
PPA-370-2066
Turbines
8
Turbine height
131 m
Address (REPD)
Altercannoch B7027, Main Street, Barrhill-Council Boundary, South From Barrhill, Barrhill, Girvan
Council area (by location)
South Ayrshire
Time to decision
99 weeks
REPD reference
2847

Who decides

ApplicationsSouth AyrshireUK
Decided applications (solar, wind, battery)2010,236
Refused12 (60%)19%
Solar refused0 of 612%
Onshore wind refused12 of 1345%
Battery storage refused0 of 116%
Median time from submission to decision41.7 weeks17.0 weeks
Appeals lodged / allowed5 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Chirmorie Wind Farmwind farm80approved, not built1.9
Arecleoch Wind Farm (extension)battery storage20under construction3.3
Arecleoch Windfarmwind farm120operational3.3
Arecleoch Wind Farm (extension)wind farm72.8under construction3.3
Corwar Wind Farmwind farm16.4refused on appeal4.5
Mark Hillwind farm56operational5.0
Hill of Ochiltreewind farm23refused9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.0833, -4.7511).