Crutherland Farm, Crutherland Highway (22.8 MW battery storage)
Crutherland Farm, Crutherland Highway is a 22.8 MW battery storage project in East Suffolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 6 November 2024; the record was last updated on 19 November 2024.
22.8 MWbattery storage
refusedstatus in REPD
19 November 2024record last updated
East Suffolkcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 12 March 2024 | Application submitted |
| 6 November 2024 | Refused by the planning authority |
Project details
- Technology
- battery storage (stand-alone storage)
- Capacity
- 22.8 MW
- Status (REPD)
- refused
- Record last updated
- 19 November 2024
- Operator or applicant
- Private Developer
- Planning authority
- South Lanarkshire
- Planning application reference
- P/24/0307
- Address (REPD)
- Crutherland Farm, Crutherland Highway, East Kilbride, Glasgow
- Council area (by location)
- East Suffolk
- Time to decision
- 34 weeks
- Name in REPD
- Crutherland Farm, Crutherland Highway - Battery Energy Storage
- REPD reference
- 15523
Who decides
| Applications | South Lanarkshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 89 | 10,236 |
| Refused | 30 (34%) | 19% |
| Solar refused | 2 of 20 | 12% |
| Onshore wind refused | 21 of 56 | 45% |
| Battery storage refused | 7 of 13 | 16% |
| Median time from submission to decision | 47.4 weeks | 17.0 weeks |
| Appeals lodged / allowed | 6 / 5 | — |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.2351, 1.6894).