Energy Projects Near You

Solar, wind and battery projects near Leiston (IP16)

5 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of IP16 (East Suffolk): 4 approved but not yet running. The largest live scheme is Town Farm (21 MW solar farm, approved on 5 January 2024, not yet built), 7.4 km away. Offshore, 1 wind farm is recorded within 40 km; the nearest is Greater Gabbard Wind Farm (504 MW, operational), 39.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5projects within 10 km
0awaiting a decision
4approved, not running
0operational

Projects within 10 km of IP16

Projects of 1 MW and more (3)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Town Farmsolar farmsolar farm21approved, not builtupdated Jun 2024Jan 2022granted Jan 2024Jun 2024East Suffolk7.4
Crutherland Farm, Crutherland Highwaybattery storagebattery storage22.8refusedupdated Nov 2024Mar 2024refused Nov 2024Nov 2024East Suffolk8.0
Haw Wood, Thoringtonsolar farmsolar farm1approved, not builtupdated Feb 2026Aug 2024granted Dec 2024Feb 2026East Suffolk9.8
Smaller schemes under 1 MW, mostly rooftop solar (2)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Beach View Holiday Park, Sizewell Common Solar Arrayssolar farmsolar farm—approved, not builtupdated Jun 2026Feb 2026granted Apr 2026Jun 2026East Suffolk2.5
East Green Farm, Kelsale Cum Carltonsolar farmsolar farm0.2approved, not built may be out of dateupdated Jun 2022May 2022granted Oct 2022Jun 2022East Suffolk5.6

Distance from the average position of the IP16 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm4040022.2
Battery storage100010

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Greater Gabbard Wind Farm504operationalupdated Oct 201939.7

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How East Suffolk decides solar, wind and battery applications

ApplicationsEast SuffolkUK
Decided applications (solar, wind, battery)5510,236
Refused10 (18%)19%
Solar refused3 of 3812%
Onshore wind refused5 of 845%
Battery storage refused2 of 916%
Median time from submission to decision15.0 weeks17.0 weeks
Appeals lodged / allowed0 / 3—

All projects in East Suffolk

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near IP16, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.