Town Farm (21 MW solar farm)

Town Farm is a 21 MW solar farm project in East Suffolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 5 January 2024, not yet built; the record was last updated on 3 June 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

21 MWsolar farm
approved, not builtstatus in REPD
3 June 2024record last updated
East Suffolkcouncil area

Planning timeline

DateStage
5 January 2022Application submitted
5 January 2024Planning permission granted
5 January 2027Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
21 MW
Status (REPD)
approved, not built
Record last updated
3 June 2024
Operator or applicant
British Solar Renewables
Planning authority
East Suffolk
Planning application reference
DC/21/5515/FUL
Site area
28.7 ha
Address (REPD)
Town Farm, Town Farm Lane, Kelsale Cum Carlton, Saxmundham
Council area (by location)
East Suffolk
Time to decision
104 weeks
Name in REPD
Town Farm - Solar panels
REPD reference
9296

Who decides

ApplicationsEast SuffolkUK
Decided applications (solar, wind, battery)5510,236
Refused10 (18%)19%
Solar refused3 of 3812%
Onshore wind refused5 of 845%
Battery storage refused2 of 916%
Median time from submission to decision15.0 weeks17.0 weeks
Appeals lodged / allowed0 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Parham Airfield (Great Glenham)solar farm17.5operational8.5
New Road Solar Farmsolar farm49.9approved, not built8.7
Hill Farmsolar farm15.9abandoned9.0
Parham Airfield (wind)wind farm13.8abandoned9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.2487, 1.5019).