Parham Airfield (wind) (13.8 MW)

Parham Airfield (wind) is a 13.8 MW wind farm project in East Suffolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 1 July 2011.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

13.8 MWwind farm
abandonedstatus in REPD
1 July 2011record last updated
East Suffolkcouncil area

Planning timeline

DateStage
1 March 2005Application submitted
5 October 2005Planning permission granted
5 October 2011Permission expired

Project details

Technology
wind farm
Capacity
13.8 MW
Status (REPD)
abandoned
Record last updated
1 July 2011
Operator or applicant
Your Energy
Planning authority
East Suffolk
Planning application reference
C05/0400
Turbines
6
Address (REPD)
Parham Airfield between Great Glenham and Marlesford
Council area (by location)
East Suffolk
Time to decision
31 weeks
REPD reference
3262

Who decides

ApplicationsEast SuffolkUK
Decided applications (solar, wind, battery)5510,236
Refused10 (18%)19%
Solar refused3 of 3812%
Onshore wind refused5 of 845%
Battery storage refused2 of 916%
Median time from submission to decision15.0 weeks17.0 weeks
Appeals lodged / allowed0 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
New Road Solar Farmsolar farm49.9approved, not built0.6
Parham Airfield (Great Glenham)solar farm17.5operational1.2
Hacheston Solar farmsolar farm25refused on appeal2.5
Glevering Park House, Glevering Estatesolar farm20application submitted4.7
Kettleburgh Road Easton Solar Panels & Battery Storagesolar farm49.9application submitted6.4
Park Farmsolar farm21approved, not built6.6
Town Farmsolar farm21approved, not built9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.1984, 1.3934).