Parham Airfield (Great Glenham) (17.5 MW solar farm)

Parham Airfield (Great Glenham) is a 17.5 MW solar farm project in East Suffolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 4 December 2013; the record was last updated on 1 October 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

17.5 MWsolar farm
operationalstatus in REPD
1 October 2014record last updated
East Suffolkcouncil area

Planning timeline

DateStage
27 September 2012Application submitted
5 April 2013Planning permission granted
1 May 2013Construction started
4 December 2013Operational

Project details

Technology
solar farm
Capacity
17.5 MW
Status (REPD)
operational
Record last updated
1 October 2014
Operator or applicant
AG Renewables Ltd
Planning authority
East Suffolk
Planning application reference
C/12/2067
Address (REPD)
North of Runway Farm, Great Glemham, Suffolk
Council area (by location)
East Suffolk
Time to decision
27 weeks
REPD reference
2281

Who decides

ApplicationsEast SuffolkUK
Decided applications (solar, wind, battery)5510,236
Refused10 (18%)19%
Solar refused3 of 3812%
Onshore wind refused5 of 845%
Battery storage refused2 of 916%
Median time from submission to decision15.0 weeks17.0 weeks
Appeals lodged / allowed0 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
New Road Solar Farmsolar farm49.9approved, not built0.6
Parham Airfield (wind)wind farm13.8abandoned1.2
Hacheston Solar farmsolar farm25refused on appeal3.5
Glevering Park House, Glevering Estatesolar farm20application submitted5.1
Park Farmsolar farm21approved, not built6.6
Kettleburgh Road Easton Solar Panels & Battery Storagesolar farm49.9application submitted7.3
Town Farmsolar farm21approved, not built8.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.1965, 1.4101).