Solar, wind and battery projects near Saxmundham (IP17)

9 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of IP17 (East Suffolk): 7 approved but not yet running, 1 operational. The largest live scheme is New Road Solar Farm (49.9 MW solar farm, approved on 13 October 2021, not yet built; REPD status may be out of date), 7.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9projects within 10 km
0awaiting a decision
7approved, not running
1operational

Projects within 10 km of IP17

Projects of 1 MW and more (5)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Town Farmsolar farmsolar farm21approved, not builtupdated Jun 2024Jan 2022granted Jan 2024Jun 2024East Suffolk2.0
Haw Wood, Thoringtonsolar farmsolar farm1approved, not builtupdated Feb 2026Aug 2024granted Dec 2024Feb 2026East Suffolk7.4
Parham Airfield (Great Glenham)solar farmsolar farm17.5operationalupdated Oct 2014Sep 2012granted Apr 2013Oct 2014East Suffolk7.4
New Road Solar Farmsolar farmsolar farm49.9approved, not built may be out of dateupdated Dec 2021Mar 2021granted Oct 2021Dec 2021East Suffolk7.7
Parham Airfield (wind)wind farmwind farm13.8abandonedupdated Jul 2011Mar 2005granted Oct 2005Jul 2011East Suffolk8.3
Smaller schemes under 1 MW, mostly rooftop solar (4)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
East Green Farm, Kelsale Cum Carltonsolar farmsolar farm0.2approved, not built may be out of dateupdated Jun 2022May 2022granted Oct 2022Jun 2022East Suffolk1.3
Earlsway Farm, Bramfieldsolar farmsolar farm0.2approved, not builtupdated Feb 2024Dec 2023granted Feb 2024Feb 2024East Suffolk7.3
Beach View Holiday Park, Sizewell Common Solar Arrayssolar farmsolar farm—approved, not builtupdated Jun 2026Feb 2026granted Apr 2026Jun 2026East Suffolk8.6
Home Farm, Halesworth Roadrooftop solarrooftop solar0.3approved, not builtupdated Jun 2026Mar 2026granted Apr 2026Jun 2026East Suffolk8.9

Distance from the average position of the IP17 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm7061072.4
Rooftop solar101000.3
Wind farm100000

MW in pipeline: pending, approved and under-construction capacity.

How East Suffolk decides solar, wind and battery applications

ApplicationsEast SuffolkUK
Decided applications (solar, wind, battery)5510,236
Refused10 (18%)19%
Solar refused3 of 3812%
Onshore wind refused5 of 845%
Battery storage refused2 of 916%
Median time from submission to decision15.0 weeks17.0 weeks
Appeals lodged / allowed0 / 3—

All projects in East Suffolk

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near IP17, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.