Energy Projects Near You

New Road Solar Farm (49.9 MW)

New Road Solar Farm is a 49.9 MW solar farm project in East Suffolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 13 October 2021, not yet built; the record was last updated on 7 December 2021. REPD also records that the planning permission expired on 13 October 2024, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtmay be out of datestatus in REPD
7 December 2021record last updated
East Suffolkcouncil area

REPD also records that the planning permission expired on 13 October 2024, so the project may not go ahead in this form.

Planning timeline

DateStage
1 March 2021Application submitted
13 October 2021Planning permission granted
13 October 2024Permission expired

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
7 December 2021
Operator or applicant
Low Carbon UK Solar Investment Co Limited
Planning authority
East Suffolk
Planning application reference
DC/21/1001/FUL
Site area
74.0 ha
Address (REPD)
North & S/O New Road E/O Silverlace, Green Parham Woodbridge
Council area (by location)
East Suffolk
Time to decision
32 weeks
REPD reference
9625

Who decides

ApplicationsEast SuffolkUK
Decided applications (solar, wind, battery)5510,236
Refused10 (18%)19%
Solar refused3 of 3812%
Onshore wind refused5 of 845%
Battery storage refused2 of 916%
Median time from submission to decision15.0 weeks17.0 weeks
Appeals lodged / allowed0 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Parham Airfield (Great Glenham)solar farm17.5operational0.6
Parham Airfield (wind)wind farm13.8abandoned0.6
Hacheston Solar farmsolar farm25refused on appeal3.1
Glevering Park House, Glevering Estatesolar farm20application submitted5.1
Park Farmsolar farm21approved, not built6.8
Kettleburgh Road Easton Solar Panels & Battery Storagesolar farm49.9application submitted7.0
Town Farmsolar farm21approved, not built8.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.1995, 1.4025).