Energy Projects Near You

Solar, wind and battery projects near Woodbridge (IP13)

11 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of IP13 (East Suffolk): 4 are waiting for a planning decision, 2 approved but not yet running, 2 operational. The largest live scheme is Kettleburgh Road Easton Solar Panels & Battery Storage (50 MW battery storage, application submitted on 10 July 2025, no decision recorded), 2.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11projects within 10 km
4awaiting a decision
2approved, not running
2operational

Projects within 10 km of IP13

Projects of 1 MW and more (9)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Kettleburgh Road Easton Solar Panels & Battery Storagebattery storagebattery storage50application submittedupdated Sep 2025Jul 2025—Sep 2025East Suffolk2.8
Kettleburgh Road Easton Solar Panels & Battery Storagesolar farmsolar farm49.9application submittedupdated Sep 2025Jul 2025—Sep 2025East Suffolk2.8
Hacheston Solar farmsolar farmsolar farm25refused on appealupdated Jun 2014Sep 2012refused Feb 2013Jun 2014East Suffolk2.9
Glevering Park House, Glevering Estatesolar farmsolar farm20application submittedupdated Sep 2025Jul 2025—Sep 2025East Suffolk4.2
Parham Airfield (wind)wind farmwind farm13.8abandonedupdated Jul 2011Mar 2005granted Oct 2005Jul 2011East Suffolk5.1
New Road Solar Farmsolar farmsolar farm49.9approved, not built may be out of dateupdated Dec 2021Mar 2021granted Oct 2021Dec 2021East Suffolk5.7
Parham Airfield (Great Glenham)solar farmsolar farm17.5operationalupdated Oct 2014Sep 2012granted Apr 2013Oct 2014East Suffolk6.1
Lower Ufford Lanesolar farmsolar farm1.1operationalupdated Jul 2015Jul 2014granted Oct 2014Jul 2015East Suffolk6.7
Park Farmsolar farmsolar farm21approved, not builtupdated Jul 2024Dec 2021granted Jun 2024Jul 2024East Suffolk7.0
Smaller schemes under 1 MW, mostly rooftop solar (2)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
The Street, Hachestonbattery storagebattery storage—application submittedupdated Feb 2026Jan 2026—Feb 2026East Suffolk3.3
Wilford Bridge Road, Station Road - Micro Energy Storage Unitbattery storagebattery storage0.2application withdrawnupdated Apr 2025Jan 2025—Apr 2025East Suffolk9.5

Distance from the average position of the IP13 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm72221141
Wind farm100000
Battery storage3200050

MW in pipeline: pending, approved and under-construction capacity.

How East Suffolk decides solar, wind and battery applications

ApplicationsEast SuffolkUK
Decided applications (solar, wind, battery)5510,236
Refused10 (18%)19%
Solar refused3 of 3812%
Onshore wind refused5 of 845%
Battery storage refused2 of 916%
Median time from submission to decision15.0 weeks17.0 weeks
Appeals lodged / allowed0 / 3—

All projects in East Suffolk

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near IP13, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.