Hacheston Solar farm (25 MW)

Hacheston Solar farm is a 25 MW solar farm project in East Suffolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 22 May 2014; the record was last updated on 2 June 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

25 MWsolar farm
refused on appealstatus in REPD
2 June 2014record last updated
East Suffolkcouncil area

Planning timeline

DateStage
4 September 2012Application submitted
8 February 2013Refused by the planning authority
22 May 2014Appeal refused

Project details

Technology
solar farm
Capacity
25 MW
Status (REPD)
refused on appeal
Record last updated
2 June 2014
Operator or applicant
Hive Energy
Planning authority
East Suffolk
Planning application reference
C/12/1899
Appeal reference
C/12/1899
Address (REPD)
N/O Easton Lane, Hacheston, Woodbridge, Suffolk, IP13
Council area (by location)
East Suffolk
Time to decision
22 weeks
REPD reference
1602

Who decides

ApplicationsEast SuffolkUK
Decided applications (solar, wind, battery)5510,236
Refused10 (18%)19%
Solar refused3 of 3812%
Onshore wind refused5 of 845%
Battery storage refused2 of 916%
Median time from submission to decision15.0 weeks17.0 weeks
Appeals lodged / allowed0 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Parham Airfield (wind)wind farm13.8abandoned2.5
Glevering Park House, Glevering Estatesolar farm20application submitted2.6
New Road Solar Farmsolar farm49.9approved, not built3.1
Parham Airfield (Great Glenham)solar farm17.5operational3.5
Kettleburgh Road Easton Solar Panels & Battery Storagesolar farm49.9application submitted3.9
Park Farmsolar farm21approved, not built5.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.1852, 1.3628).