Glevering Park House, Glevering Estate (20 MW solar farm)

Glevering Park House, Glevering Estate is a 20 MW solar farm project in East Suffolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 31 July 2025, no decision recorded; the record was last updated on 12 September 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWsolar farm
application submittedstatus in REPD
12 September 2025record last updated
East Suffolkcouncil area

Planning timeline

DateStage
31 July 2025Application submitted

Project details

Technology
solar farm
Capacity
20 MW
Status (REPD)
application submitted
Record last updated
12 September 2025
Operator or applicant
Grupotec
Planning authority
East Suffolk
Planning application reference
DC/25/2997/FUL
Site area
37.0 ha
Address (REPD)
S/O Easton Lane, Glevering Park House, Glevering Estate, Wickham Market, Woodbridge
Council area (by location)
East Suffolk
Name in REPD
Glevering Park House, Glevering Estate - Solar Panels
REPD reference
18304

Who decides

ApplicationsEast SuffolkUK
Decided applications (solar, wind, battery)5510,236
Refused10 (18%)19%
Solar refused3 of 3812%
Onshore wind refused5 of 845%
Battery storage refused2 of 916%
Median time from submission to decision15.0 weeks17.0 weeks
Appeals lodged / allowed0 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hacheston Solar farmsolar farm25refused on appeal2.6
Park Farmsolar farm21approved, not built2.9
Kettleburgh Road Easton Solar Panels & Battery Storagesolar farm49.9application submitted3.1
Parham Airfield (wind)wind farm13.8abandoned4.7
New Road Solar Farmsolar farm49.9approved, not built5.1
Parham Airfield (Great Glenham)solar farm17.5operational5.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.1615, 1.3611).