Greater Gabbard received its consent quickly, yet took more than three years to build. This offshore wind farm of 140 turbines at 3.6 MW each stands in the North Sea, 33 km from the coast of East Suffolk; the nearest postcode district is IP15 (Aldeburgh) at 35.0 km, with IP16 at 39.7 km. According to the REPD extract for July 2026, it ranks twelfth by capacity among operational offshore wind farms in the UK.
From application to grid
Airtricity and Fluor Ltd submitted their application on 17 October 2005. Consent under Section 36 was issued on 20 February 2007, after 70 weeks, whereas this authority's median for offshore wind (listed in the register as DECC) is 95.8 weeks. Construction began on 1 July 2009, and it was only on 7 September 2012 that the wind farm became operational.
Neighbours off Suffolk
At 8.7 km, Galloper is operational at 353 MW, with its own separate decision. Further out, at 29.6 km, East Anglia 1 (714 MW) is operational, East Anglia 3 (1,400 MW) is under construction and East Anglia 1 North (800 MW) is approved, not built. The Greater Gabbard record has not been updated since 2 October 2019.