East Anglia 3 (EA 3) offshore wind farm

East Anglia 3 (EA 3) is a 1,400 MW offshore wind farm with 100 turbines in English waters. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 June 2025; the record was last updated on 2 December 2025. Its REPD grid reference is 38 km from the nearest postcode on land (IP16 4PB, East Suffolk). As a nationally significant project, it was decided by the Secretary of State responsible for energy at the time on a Development Consent Order after examination by the Planning Inspectorate (EN010056).

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

1,400 MWoffshore wind farm
under constructionstatus in REPD
2 December 2025record last updated
38 km from land (East Suffolk)REPD location

Consent timeline

DateStage
18 November 2015Application submitted
7 August 2017Development consent granted (Secretary of State)
1 June 2025Construction started

Project details

Technology
offshore wind farm
Capacity
1,400 MW
Turbines
100
Turbine capacity
14 MW
Turbine height
282 m
Status (REPD)
under construction
Record last updated
2 December 2025
Operator or applicant
Scottish Power Renewables
Consenting authority (REPD)
The Planning Inspectorate - National Infrastructure
Application reference
EN010056
Nearest postcode on land
IP16 4PB (East Suffolk), 38.1 km from the REPD grid reference
Time to decision
90 weeks
Contracts for Difference
AR6
REPD reference
2470

Official project record at the Planning Inspectorate

Who decides

As a nationally significant project, it was decided by the Secretary of State responsible for energy at the time on a Development Consent Order after examination by the Planning Inspectorate (EN010056). All Energy Secretary decisions on solar and wind farms.

Postcode districts within 40 km

Districtkm
Aldeburgh (IP15)39.5

Straight-line distance from the centre of each postcode district to the REPD grid reference of the wind farm, which is a single point for the whole site.

Other offshore wind projects within 30 km

ProjectMWStatuskm
East Anglia 1 North (EA 4)800approved, not built<0.1
East Anglia 1 (EA 1)714operational<0.1
Greater Gabbard Wind Farm504operational29.6
Galloper Wind Farm353operational30.0

All offshore wind farms in UK waters

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database can lag behind consent decisions. Location: REPD grid reference (52.137, 2.1728).