East Anglia 1 (EA 1) offshore wind farm

East Anglia 1 (EA 1) is a 714 MW offshore wind farm with 102 turbines in English waters. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 28 July 2020; the record was last updated on 20 August 2020. Its REPD grid reference is 38 km from the nearest postcode on land (IP16 4PB, East Suffolk). As a nationally significant project, it was decided by the Secretary of State responsible for energy at the time on a Development Consent Order after examination by the Planning Inspectorate (ENO10025).

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

714 MWoffshore wind farm
operationalstatus in REPD
20 August 2020record last updated
38 km from land (East Suffolk)REPD location

Consent timeline

DateStage
21 November 2012Application submitted
17 June 2014Development consent granted (Secretary of State)
24 May 2018Construction started
28 July 2020Operational

Project details

Technology
offshore wind farm
Capacity
714 MW
Turbines
102
Turbine capacity
7 MW
Status (REPD)
operational
Record last updated
20 August 2020
Operator or applicant
Scottish Power Renewables
Consenting authority (REPD)
The Planning Inspectorate - National Infrastructure
Application reference
ENO10025
Nearest postcode on land
IP16 4PB (East Suffolk), 38.1 km from the REPD grid reference
Time to decision
82 weeks
Contracts for Difference
AR1
REPD reference
2524

Who decides

As a nationally significant project, it was decided by the Secretary of State responsible for energy at the time on a Development Consent Order after examination by the Planning Inspectorate (ENO10025). All Energy Secretary decisions on solar and wind farms.

Postcode districts within 40 km

Districtkm
Aldeburgh (IP15)39.5

Straight-line distance from the centre of each postcode district to the REPD grid reference of the wind farm, which is a single point for the whole site.

Other offshore wind projects within 30 km

ProjectMWStatuskm
East Anglia 1 North (EA 4)800approved, not built<0.1
East Anglia 3 (EA 3)1,400under construction<0.1
Greater Gabbard Wind Farm504operational29.6
Galloper Wind Farm353operational30.0

All offshore wind farms in UK waters

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database can lag behind consent decisions. Location: REPD grid reference (52.137, 2.1728).