Galloper and Greater Gabbard lie 8.7 km apart off East Suffolk, but they are two separate projects with different turbines and different approval routes. Galloper's REPD point sits 42 km from the IP12 2NY postcode, and there are no postcode districts within 40 km.
How Galloper differs from its neighbour
Galloper has 56 turbines of 6.3 MW each, Greater Gabbard 140 of 3.6 MW: fewer machines, each one more powerful, 353 MW in total against 504. Its neighbour received Section 36 consent in 2007. Galloper, applied for by RWE Npower Renewables on 21 November 2011, went through examination by the Planning Inspectorate (EN010003) and on 24 May 2013 was granted consent as a nationally significant infrastructure project (DCO): 79 weeks against a median of 84.4. Construction ran from 29 July 2016 to 30 March 2018. Within 30 km, East Anglia 1 is operational (714 MW) and East Anglia 3 is under construction (1,400 MW). The Galloper record was last updated on 2 October 2019; the data come from the July 2026 extract.