Cwmpenanner (24.2 MW wind farm)

Cwmpenanner is a 24.2 MW wind farm project in Conwy, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 26 November 2004; the record was last updated on 7 December 2010.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

24.2 MWwind farm
refusedstatus in REPD
7 December 2010record last updated
Conwycouncil area

Planning timeline

DateStage
4 January 2004Application submitted
26 November 2004Refused by the planning authority

Project details

Technology
wind farm
Capacity
24.2 MW
Status (REPD)
refused
Record last updated
7 December 2010
Operator or applicant
Zepher
Planning authority
Gwynedd
Planning application reference
0/28528
Address (REPD)
Cwm Penanner, Cerrid-Y-Drudion Corwen Conwy
Council area (by location)
Conwy
Time to decision
47 weeks
REPD reference
3250

Who decides

ApplicationsGwyneddUK
Decided applications (solar, wind, battery)1910,236
Refused6 (32%)19%
Solar refused3 of 1312%
Onshore wind refused2 of 345%
Battery storage refused1 of 316%
Median time from submission to decision17.4 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Moel Rhiwlug Wind Farmwind farm19.2application withdrawn9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.0041, -3.6134).