Energy Projects Near You

Ellands Farm (18 MW wind farm)

Ellands Farm is an 18 MW wind farm project in North Northamptonshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 17 May 2006; the record was last updated on 6 April 2007.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18 MWwind farm
refusedstatus in REPD
6 April 2007record last updated
North Northamptonshirecouncil area

Planning timeline

DateStage
20 February 2006Application submitted
17 May 2006Refused by the planning authority

Project details

Technology
wind farm
Capacity
18 MW
Status (REPD)
refused
Record last updated
6 April 2007
Operator or applicant
Enertrag Ltd
Planning authority
North Northamptonshire
Planning application reference
EN/06/00292/FUL
Turbines
6
Address (REPD)
Barnwell Road, Hemington, Peterborough
Council area (by location)
North Northamptonshire
Time to decision
12 weeks
REPD reference
3013

Who decides

ApplicationsNorth NorthamptonshireUK
Decided applications (solar, wind, battery)6810,236
Refused11 (16%)19%
Solar refused2 of 4412%
Onshore wind refused5 of 1145%
Battery storage refused4 of 1316%
Median time from submission to decision11.4 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Foxholes Farm, Roman Roadsolar farm49.9application submitted6.6
RAF Molesworth Wind Farmwind farm15refused7.9
Wood Lodge Farm, Huntingdon Road Solar Farmsolar farm50application submitted8.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.4439, -0.405).