Energy Projects Near You

Glenkerie Wind Farm Extension (15 MW)

Glenkerie Wind Farm Extension is a 15 MW wind farm project in Scottish Borders, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 29 July 2018; the record was last updated on 23 September 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15 MWwind farm
permission expiredstatus in REPD
23 September 2020record last updated
Scottish Borderscouncil area

Planning timeline

DateStage
14 May 2013Application submitted
1 December 2014Refused by the planning authority
5 March 2015Appeal lodged
29 July 2015Planning permission granted
29 July 2015Appeal allowed
29 July 2018Permission expired

Project details

Technology
wind farm
Capacity
15 MW
Status (REPD)
permission expired
Record last updated
23 September 2020
Operator or applicant
Muirhall Energy (formerly Infinis)
Planning authority
Scottish Borders
Planning application reference
13/00552/FUL
Appeal reference
PPA-140-2052
Turbines
6
Address (REPD)
Kingledores Farm, Broughton, Biggar, Strathclyde
Council area (by location)
Scottish Borders
Time to decision
115 weeks
REPD reference
4578

Who decides

ApplicationsScottish BordersUK
Decided applications (solar, wind, battery)6110,236
Refused28 (46%)19%
Solar refused0 of 1312%
Onshore wind refused26 of 4345%
Battery storage refused2 of 516%
Median time from submission to decision51.3 weeks17.0 weeks
Appeals lodged / allowed11 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Glenkerie Wind Farmwind farm22operational<0.1
Tweed Valley, Southern Uplands - Oliver Forest Wind Farmbattery storage23application submitted8.0
Tweed Valley, Southern Uplands - Oliver Forest Wind Farmwind farm50.4application submitted8.0
Whitelaw Brae Wind Farmwind farm57under construction8.0
Clyde Wind Farm Extension (Clyde 2)wind farm173operational8.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.5385, -3.4205).