Glenkerie Wind Farm (22 MW)

Glenkerie Wind Farm is a 22 MW wind farm project in Scottish Borders, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 February 2012; the record was last updated on 6 March 2012.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

22 MWwind farm
operationalstatus in REPD
6 March 2012record last updated
Scottish Borderscouncil area

Planning timeline

DateStage
20 December 2007Application submitted
8 September 2008Planning permission granted
1 April 2011Construction started
1 February 2012Operational

Project details

Technology
wind farm
Capacity
22 MW
Status (REPD)
operational
Record last updated
6 March 2012
Operator or applicant
Novera Energy
Planning authority
Scottish Borders
Planning application reference
07/02478/FUL
Turbines
11
Address (REPD)
Kingledores Farm, Broughton, Biggar, Strathclyde. ML12 6QL
Council area (by location)
Scottish Borders
Time to decision
38 weeks
REPD reference
3538

Who decides

ApplicationsScottish BordersUK
Decided applications (solar, wind, battery)6110,236
Refused28 (46%)19%
Solar refused0 of 1312%
Onshore wind refused26 of 4345%
Battery storage refused2 of 516%
Median time from submission to decision51.3 weeks17.0 weeks
Appeals lodged / allowed11 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Glenkerie Wind Farm Extensionwind farm15permission expired<0.1
Tweed Valley, Southern Uplands - Oliver Forest Wind Farmbattery storage23application submitted8.0
Tweed Valley, Southern Uplands - Oliver Forest Wind Farmwind farm50.4application submitted8.0
Whitelaw Brae Wind Farmwind farm57under construction8.0
Clyde Wind Farm Extension (Clyde 2)wind farm173operational8.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.5385, -3.4205).