Green Volt offshore wind farm

Green Volt - Offshore Wind Farm is a 560 MW offshore wind farm with 35 turbines in Scottish waters. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 19 April 2024, not yet built; the record was last updated on 28 May 2024. REPD's grid reference for it is not at the wind farm site, so no distance from the coast is given. As an offshore wind farm in Scottish waters, it is consented by Scottish Ministers; REPD names Marine Scotland as the consenting authority.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

560 MWoffshore wind farm
approved, not builtstatus in REPD
28 May 2024record last updated
REPD point not at the siteREPD location

Consent timeline

DateStage
20 January 2023Application submitted
19 April 2024Marine licence and Section 36 consent granted (Scottish Ministers)

Project details

Technology
offshore wind farm
Capacity
560 MW
Turbines
35
Turbine capacity
16 MW
Turbine height
270 m
Status (REPD)
approved, not built
Record last updated
28 May 2024
Operator or applicant
Flotation Energy / Vårgrønn
Consenting authority (REPD)
Marine Scotland
Application reference
not recorded
Time to decision
65 weeks
Contracts for Difference
AR6
REPD reference
11851

Who decides

As an offshore wind farm in Scottish waters, it is consented by Scottish Ministers; REPD names Marine Scotland as the consenting authority.

All offshore wind farms in UK waters

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database can lag behind consent decisions.