Energy Projects Near You

Hardybarn Lane, Green Fairfield (40 MW battery storage)

Hardybarn Lane, Green Fairfield is a 40 MW battery storage project in High Peak, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 1 June 2026, no decision recorded; the record was last updated on an unrecorded date.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

40 MWbattery storage
application submittedstatus in REPD
not recordedrecord last updated
High Peakcouncil area

Planning timeline

DateStage
1 June 2026Application submitted

Project details

Technology
battery storage (stand-alone storage)
Capacity
40 MW
Status (REPD)
application submitted
Record last updated
not recorded
Operator or applicant
S & L Energy Limited
Planning authority
High Peak
Planning application reference
HPK/2026/0188
Address (REPD)
W/O Hardybarn Lane, Green Fairfield, Buxton
Council area (by location)
High Peak
Name in REPD
Hardybarn Lane, Green Fairfield - Battery Energy Storage Facility
REPD reference
21092

Earlier applications for this site

ApplicationMWSubmittedOutcome
Hardybarn Lane, Green Fairfield HPK/2025/00464026 February 2025replaced by a revised application

Who decides

ApplicationsHigh PeakUK
Decided applications (solar, wind, battery)1510,236
Refused1 (7%)19%
Solar refused1 of 812%
Battery storage refused0 of 716%
Median time from submission to decision8.0 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Waterswallows Road - Buxton Battery Storage Equipmentbattery storage15operational0.5
Waterswallows Road - Buxton Battery Storage Equipmentbattery storage15operational0.5
Dolly Lane, Buxworth Battery Storage Facility & Sub Stationbattery storage13approved, not built9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.2736, -1.8727).