Energy Projects Near You

Waterswallows Road - Buxton Battery Storage Equipment (15 MW, REPD 20381)

Waterswallows Road - Buxton Battery Storage Equipment is a 15 MW battery storage project in High Peak, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 11 April 2024; the record was last updated on 13 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15 MWbattery storage
operationalstatus in REPD
13 February 2026record last updated
High Peakcouncil area

Planning timeline

DateStage
11 February 2022Application submitted
8 April 2022Planning permission granted
1 January 2024Construction started
11 April 2024Operational

Project details

Technology
battery storage (stand-alone storage)
Capacity
15 MW
Status (REPD)
operational
Record last updated
13 February 2026
Operator or applicant
Atlantic Green
Planning authority
High Peak
Planning application reference
HPK/2022/0046
Address (REPD)
STOR Facility, Waterswallows Road, Green Fairfield, Buxton
Council area (by location)
High Peak
Time to decision
8 weeks
REPD reference
20381

Who decides

ApplicationsHigh PeakUK
Decided applications (solar, wind, battery)1510,236
Refused1 (7%)19%
Solar refused1 of 812%
Battery storage refused0 of 716%
Median time from submission to decision8.0 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Waterswallows Road - Buxton Battery Storage Equipmentbattery storage15operational<0.1
Hardybarn Lane, Green Fairfieldbattery storage40application submitted0.5
Dolly Lane, Buxworth Battery Storage Facility & Sub Stationbattery storage13approved, not built9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.2727, -1.8794).