Energy Projects Near You

Higher Bye Farm (6.8 MW solar farm)

Higher Bye Farm is a 6.8 MW solar farm project in Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 19 March 2015; the record was last updated on 28 May 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.8 MWsolar farm
operationalstatus in REPD
28 May 2015record last updated
Somersetcouncil area

Planning timeline

DateStage
23 May 2014Application submitted
26 September 2014Planning permission granted
1 January 2015Construction started
19 March 2015Operational

Project details

Technology
solar farm
Capacity
6.8 MW
Status (REPD)
operational
Record last updated
28 May 2015
Operator or applicant
Anesco
Planning authority
Somerset
Planning application reference
3/26/14/013
Address (REPD)
Land at Higher Bye Farm, Higher Bye Farm
Council area (by location)
Somerset
Time to decision
18 weeks
REPD reference
2342

Who decides

ApplicationsSomersetUK
Decided applications (solar, wind, battery)18510,236
Refused46 (25%)19%
Solar refused34 of 15312%
Onshore wind refused9 of 1045%
Battery storage refused3 of 2216%
Median time from submission to decision14.0 weeks17.0 weeks
Appeals lodged / allowed17 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
The Transmitting Station, Williton Solar Farm (Wyndham Estate)solar farm25approved, not built0.9
The Transmitting Station, Williton Battery Storage (Wyndham Estate)battery storage20approved, not built0.9
Smithyard Lanebattery storage15approved, not built1.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.1726, -3.3597).