Energy Projects Near You

Solar, wind and battery projects near Watchet (TA23)

8 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TA23 (Somerset): 5 approved but not yet running, 1 operational. The largest live scheme is The Transmitting Station, Williton Solar Farm (Wyndham Estate) (25 MW solar farm, approved on 28 May 2024, not yet built), 1.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8projects within 10 km
0awaiting a decision
5approved, not running
1operational

Projects within 10 km of TA23

Projects of 1 MW and more (6)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Smithyard Lanebattery storagebattery storage15approved, not built may be out of dateupdated Mar 2022Feb 2022granted Feb 2023Mar 2022Somerset0.9
Higher Bye Farmsolar farmsolar farm6.8operationalupdated May 2015May 2014granted Sep 2014May 2015Somerset1.2
The Transmitting Station, Williton Solar Farm (Wyndham Estate)solar farmsolar farm25approved, not builtupdated Feb 2026Dec 2021granted May 2024Feb 2026Somerset1.4
The Transmitting Station, Williton Battery Storage (Wyndham Estate)battery storagebattery storage20approved, not builtupdated Feb 2026Dec 2021granted May 2024Feb 2026Somerset1.4
Brendon Roadbattery storagebattery storage3permission expiredupdated Nov 2023Aug 2021granted Mar 2023Nov 2023Somerset2.3
Aller Farmsolar farmsolar farm4.7refused on appealupdated Feb 2016Sep 2014refused Apr 2015Feb 2016Somerset3.2
Smaller schemes under 1 MW, mostly rooftop solar (2)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Doniford Holiday Village, Sea Lanerooftop solarrooftop solar0.3approved, not builtupdated Feb 2023Dec 2022granted Feb 2023Feb 2023Somerset4.3
Seaward Wayrooftop solarrooftop solar0.2approved, not builtupdated Aug 2021Jun 2021granted Aug 2021Aug 2021Somerset9.0

Distance from the average position of the TA23 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm3011125
Rooftop solar202000.4
Battery storage3020035

MW in pipeline: pending, approved and under-construction capacity.

How Somerset decides solar, wind and battery applications

ApplicationsSomersetUK
Decided applications (solar, wind, battery)18510,236
Refused46 (25%)19%
Solar refused34 of 15312%
Onshore wind refused9 of 1045%
Battery storage refused3 of 2216%
Median time from submission to decision14.0 weeks17.0 weeks
Appeals lodged / allowed17 / 9—

All projects in Somerset

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near TA23, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.