Energy Projects Near You

Solar, wind and battery projects near Taunton (TA4)

17 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TA4 (Somerset): 1 is waiting for a planning decision, 4 approved but not yet running, 8 operational. The largest live scheme is The Village Of Halse (25 MW solar farm, approved on 26 January 2024, not yet built), 6.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

17projects within 10 km
1awaiting a decision
4approved, not running
8operational

Projects within 10 km of TA4

Projects of 1 MW and more (14)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Grove Farm (solar)solar farmsolar farm3.5operationalupdated May 2015Dec 2013granted Feb 2014May 2015Somerset0.6
Glebe Farm Solar Parksolar farmsolar farm4.2refusedupdated Dec 2013Apr 2013refused Jun 2013Dec 2013Somerset1.5
Pixford Fruit Farmsolar farmsolar farm5refused on appealupdated Sep 2016Jun 2015refused Nov 2015Sep 2016Somerset4.5
Halse Farmsolar farmsolar farm8.2operationalupdated Jun 2013Jun 2012granted Sep 2012Jun 2013Somerset4.5
Sandys Moor Roadsolar farmsolar farm2.9operationalupdated Feb 2014Nov 2012granted Feb 2013Feb 2014Somerset4.6
Sandhill Solar Parksolar farmsolar farm2operationalupdated Mar 2013Nov 2010granted Jan 2011Mar 2013Somerset5.1
The Village Of Halsesolar farmsolar farm25approved, not builtupdated Jan 2024Oct 2022granted Jan 2024Jan 2024Somerset6.0
Grange Farm Solar Farmsolar farmsolar farm4.9operationalupdated Oct 2014Oct 2012granted Jan 2013Oct 2014Somerset8.1
Montys Farmsolar farmsolar farm5operationalupdated May 2016Oct 2014granted Oct 2015May 2016Somerset8.4
Aller Farmsolar farmsolar farm4.7refused on appealupdated Feb 2016Sep 2014refused Apr 2015Feb 2016Somerset8.4
New Rendy Farmsolar farmsolar farm4.8operationalupdated Mar 2014Mar 2013granted May 2013Mar 2014Somerset8.6
Fideoak Millsbattery storagebattery storage30operationalupdated Sep 2022Dec 2016granted Nov 2018Sep 2022Somerset9.8
Hele Manor Farm, Bradford On Tonebattery storagebattery storage20approved, not built may be out of dateupdated Jun 2023Sep 2022granted Apr 2023Jun 2023Somerset9.9
Taunton Substationbattery storagebattery storage49.9permission expiredupdated Sep 2020Sep 2018granted Sep 2018Sep 2020Somerset10.0
Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Blagroves Farm, Blagroves Roadrooftop solarrooftop solar0.2approved, not builtupdated Mar 2023Jan 2023granted Mar 2023Mar 2023Somerset6.1
Spring Grove House, Milverton Roadsolar farmsolar farm0.2approved, not builtupdated Mar 2026Oct 2025granted Dec 2025Mar 2026Somerset6.4
Taunton Substationbattery storagebattery storage—application submitted may be out of dateupdated Nov 2022Jul 2022—Nov 2022Somerset9.8

Distance from the average position of the TA4 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm12027325.2
Rooftop solar101000.2
Battery storage4111020

MW in pipeline: pending, approved and under-construction capacity.

How Somerset decides solar, wind and battery applications

ApplicationsSomersetUK
Decided applications (solar, wind, battery)18510,236
Refused46 (25%)19%
Solar refused34 of 15312%
Onshore wind refused9 of 1045%
Battery storage refused3 of 2216%
Median time from submission to decision14.0 weeks17.0 weeks
Appeals lodged / allowed17 / 9—

All projects in Somerset

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near TA4, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.