Solar, wind and battery projects near Taunton (TA1)
31 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TA1 (Somerset): 3 are waiting for a planning decision, 14 approved but not yet running, 11 operational. The largest live scheme is Bull Street, Creech St Michael Solar Farm (34 MW solar farm, application submitted on 19 June 2025, no decision recorded), 4.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of TA1
Projects of 1 MW and more (20)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Taunton Racecoursesolar farm | solar farm | 1.5 | operationalupdated Feb 2017 | Jan 2014 | granted Apr 2014 | Feb 2017 | Somerset | 2.4 |
| Taunton Substationbattery storage | battery storage | 49.9 | permission expiredupdated Sep 2020 | Sep 2018 | granted Sep 2018 | Sep 2020 | Somerset | 3.6 |
| Fideoak Millsbattery storage | battery storage | 30 | operationalupdated Sep 2022 | Dec 2016 | granted Nov 2018 | Sep 2022 | Somerset | 3.7 |
| RITHERDENS FARM solar parksolar farm | solar farm | 9.5 | refusedupdated Sep 2013 | May 2013 | refused Aug 2013 | Sep 2013 | Somerset | 3.7 |
| Hele Manor Farm, Bradford On Tonebattery storage | battery storage | 20 | approved, not built may be out of dateupdated Jun 2023 | Sep 2022 | granted Apr 2023 | Jun 2023 | Somerset | 4.1 |
| Bull Street, Creech St Michael Solar Farmsolar farm | solar farm | 34 | application submittedupdated Aug 2025 | Jun 2025 | — | Aug 2025 | Somerset | 4.9 |
| Montys Farmsolar farm | solar farm | 5 | operationalupdated May 2016 | Oct 2014 | granted Oct 2015 | May 2016 | Somerset | 4.9 |
| Ham Farm, Creech St Michaelsolar farm | solar farm | 20 | approved, not builtupdated Jul 2024 | Nov 2022 | granted Jun 2024 | Jul 2024 | Somerset | 5.8 |
| Lower Marsh Farmsolar farm | solar farm | 5 | operationalupdated Oct 2014 | Nov 2011 | granted Feb 2012 | Oct 2014 | Somerset | 6.0 |
| New Rendy Farmsolar farm | solar farm | 4.8 | operationalupdated Mar 2014 | Mar 2013 | granted May 2013 | Mar 2014 | Somerset | 6.9 |
| Higher Knapp Farmsolar farm | solar farm | 1.5 | operationalupdated Apr 2013 | Oct 2012 | granted Jan 2013 | Apr 2013 | Somerset | 7.5 |
| VPK Wellington, Chelston Business Parkrooftop solar | rooftop solar | 1.6 | approved, not builtupdated Sep 2025 | Jul 2025 | granted Aug 2025 | Sep 2025 | Somerset | 7.7 |
| The Village Of Halsesolar farm | solar farm | 25 | approved, not builtupdated Jan 2024 | Oct 2022 | granted Jan 2024 | Jan 2024 | Somerset | 7.7 |
| Grange Farm Solar Farmsolar farm | solar farm | 4.9 | operationalupdated Oct 2014 | Oct 2012 | granted Jan 2013 | Oct 2014 | Somerset | 8.4 |
| Sandhill Solar Parksolar farm | solar farm | 2 | operationalupdated Mar 2013 | Nov 2010 | granted Jan 2011 | Mar 2013 | Somerset | 8.4 |
| Halse Farmsolar farm | solar farm | 8.2 | operationalupdated Jun 2013 | Jun 2012 | granted Sep 2012 | Jun 2013 | Somerset | 8.8 |
| Pixford Fruit Farmsolar farm | solar farm | 5 | refused on appealupdated Sep 2016 | Jun 2015 | refused Nov 2015 | Sep 2016 | Somerset | 9.4 |
| North Newton Solar Farmsolar farm | solar farm | 30 | application submittedupdated Mar 2026 | Feb 2026 | — | Mar 2026 | Somerset | 9.6 |
| Culmhead Solar Farmsolar farm | solar farm | 7.5 | operationalupdated Apr 2014 | Sep 2012 | granted Oct 2012 | Apr 2014 | Somerset | 9.8 |
| Trickey Warrensolar farm | solar farm | 4.8 | operationalupdated Aug 2015 | Sep 2014 | granted Nov 2014 | Aug 2015 | Somerset | 9.9 |
Smaller schemes under 1 MW, mostly rooftop solar (11)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| St Margarets Hospice, Heron Driverooftop solar | rooftop solar | 0.1 | approved, not builtupdated Feb 2023 | Nov 2022 | granted Jan 2023 | Feb 2023 | Somerset | 1.7 |
| Crown Industrial Estate, Venture Wayrooftop solar | rooftop solar | 0.7 | approved, not builtupdated Jan 2023 | Nov 2022 | granted Jan 2023 | Jan 2023 | Somerset | 2.3 |
| Rivergate Houserooftop solar | rooftop solar | 0.1 | approved, not builtupdated Dec 2023 | Oct 2023 | granted Nov 2023 | Dec 2023 | Somerset | 2.5 |
| Growth Technology Limited, Norton Fitzwarrenrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2023 | Jan 2023 | granted Mar 2023 | Mar 2023 | Somerset | 2.7 |
| Hollywood Bowl Solar Voltaic Equipmentrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Dec 2021 | Dec 2021 | granted Jan 2022 | Dec 2021 | Somerset | 2.8 |
| Taunton Substationbattery storage | battery storage | — | application submitted may be out of dateupdated Nov 2022 | Jul 2022 | — | Nov 2022 | Somerset | 3.7 |
| Ham Farm, Creech St Michaelbattery storage | battery storage | — | approved, not builtupdated Jul 2024 | Nov 2022 | granted Jun 2024 | Jul 2024 | Somerset | 5.8 |
| Shearston, North Pethertonbattery storage | battery storage | — | approved, not built may be out of dateupdated Mar 2022 | Feb 2022 | granted Aug 2022 | Mar 2022 | Somerset | 8.2 |
| Blagroves Farm, Blagroves Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2023 | Jan 2023 | granted Mar 2023 | Mar 2023 | Somerset | 8.4 |
| Foundation House, Culmheadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Dec 2023 | Oct 2023 | granted Nov 2023 | Dec 2023 | Somerset | 9.4 |
| Culmhead Business Park - Ground Mounted Photovoltaic Solar Arraysolar farm | solar farm | — | approved, not builtupdated Jan 2024 | Dec 2023 | granted Jan 2024 | Jan 2024 | Somerset | 9.5 |
Distance from the average position of the TA1 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 17 | 2 | 3 | 10 | 2 | 109 |
| Rooftop solar | 8 | 0 | 8 | 0 | 0 | 3.5 |
| Battery storage | 6 | 1 | 3 | 1 | 0 | 20 |
MW in pipeline: pending, approved and under-construction capacity.
How Somerset decides solar, wind and battery applications
| Applications | Somerset | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 185 | 10,236 |
| Refused | 46 (25%) | 19% |
| Solar refused | 34 of 153 | 12% |
| Onshore wind refused | 9 of 10 | 45% |
| Battery storage refused | 3 of 22 | 16% |
| Median time from submission to decision | 14.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 17 / 9 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near TA1, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.