The Village Of Halse (25 MW solar farm)

The Village Of Halse is a 25 MW solar farm project in Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 26 January 2024, not yet built; the record was last updated on 30 January 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

25 MWsolar farm
approved, not builtstatus in REPD
30 January 2024record last updated
Somersetcouncil area

Planning timeline

DateStage
26 October 2022Application submitted
26 January 2024Planning permission granted
26 January 2027Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
25 MW
Status (REPD)
approved, not built
Record last updated
30 January 2024
Operator or applicant
Novus Renewable Services Limited
Planning authority
Somerset
Planning application reference
23/22/0028
Site area
34.3 ha
Address (REPD)
The N/O Preston Bowyer and S/O the village of Halse
Council area (by location)
Somerset
Time to decision
65 weeks
Contracts for Difference
AR6
Name in REPD
The Village Of Halse - Solar Array
REPD reference
10272

Who decides

ApplicationsSomersetUK
Decided applications (solar, wind, battery)18510,236
Refused46 (25%)19%
Solar refused34 of 15312%
Onshore wind refused9 of 1045%
Battery storage refused3 of 2216%
Median time from submission to decision14.0 weeks17.0 weeks
Appeals lodged / allowed17 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Pixford Fruit Farmsolar farm5refused on appeal1.7
Halse Farmsolar farm8.2operational2.1
Montys Farmsolar farm5operational3.3
Lower Marsh Farmsolar farm5operational4.8
Fideoak Millsbattery storage30operational4.8
Taunton Substationbattery storage49.9permission expired5.1
Hele Manor Farm, Bradford On Tonebattery storage20approved, not built5.3
RITHERDENS FARM solar parksolar farm9.5refused5.5
Tonedale Farmsolar farm5operational9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.0594, -3.1847).