RITHERDENS FARM solar park (9.5 MW)

RITHERDENS FARM solar park is a 9.5 MW solar farm project in Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 22 August 2013; the record was last updated on 23 September 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9.5 MWsolar farm
refusedstatus in REPD
23 September 2013record last updated
Somersetcouncil area

Planning timeline

DateStage
9 May 2013Application submitted
22 August 2013Refused by the planning authority

Project details

Technology
solar farm
Capacity
9.5 MW
Status (REPD)
refused
Record last updated
23 September 2013
Operator or applicant
MS POWER PROJECTS LIMITED
Planning authority
Somerset
Planning application reference
07/13/0016
Address (REPD)
LAND NORTH-WEST OF RITHERDENS FARM, BRADFORD ON TONE
Council area (by location)
Somerset
Time to decision
15 weeks
REPD reference
1121

Who decides

ApplicationsSomersetUK
Decided applications (solar, wind, battery)18510,236
Refused46 (25%)19%
Solar refused34 of 15312%
Onshore wind refused9 of 1045%
Battery storage refused3 of 2216%
Median time from submission to decision14.0 weeks17.0 weeks
Appeals lodged / allowed17 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hele Manor Farm, Bradford On Tonebattery storage20approved, not built0.4
Taunton Substationbattery storage49.9permission expired0.5
Fideoak Millsbattery storage30operational0.7
Montys Farmsolar farm5operational2.1
The Village Of Halsesolar farm25approved, not built5.5
Halse Farmsolar farm8.2operational5.8
Lower Marsh Farmsolar farm5operational6.5
Pixford Fruit Farmsolar farm5refused on appeal6.9
Tonedale Farmsolar farm5operational7.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.0136, -3.1564).